Operational Readiness Reviews
Operational Readiness Review/Readiness Assessment
Services
Dynamic Solutions, LLC provides unique services
in the preparation of the established requirements
set forth by the Department of Energy (DOE) for
startup of new nuclear facilities and for the
restart of existing nuclear facilities that have
been shut down. Nuclear facilities are activities
or operations that involve radioactive and/or
fissionable materials in such form or quantity
that a nuclear hazard potentially exists to the
employees or the general public. The DOE Order
425.1C specify a readiness review process that
demonstrate that it is safe to start (or restart)
the applicable facility. The facility must be
started (or restarted) only after documented independent
reviews of readiness have been conducted and the
approvals specified in this Order have been received.
Dynamic Solutions offers extensive working knowledge
of the DOE Order 425.1C & the Standard 3006-2000
of Operational Readiness Reviews (ORR) and Readiness
Assessments (RA). Our expertise is in providing
line-management support in the preparation, planning,
and execution of projects to integrate operational
readiness in the early stages thereby successfully
completing ORR/RA. The readiness reviews are not
intended to be tools of line management to achieve
readiness, but rather, to provide an independent
confirmation of readiness to start or restart
operations. Dynamic Solutions provides guidance
of operational preparation planning to guarantee
readiness prior to the ORR/RA process. For complex
projects, Dynamic Solutions provides a detailed,
resource-loaded schedule of project activities
to be completed for the management self-assessment,
cross-referenced with project prerequisites and
criteria for operational readiness. Dynamic Solutions
routinely manages the progress of the various
disciplines objectives to determine critical path
items.
Dynamic Solutions has eight years experience
assisting the DOE subcontractors prepare for ORR/RAs,
including preparing Plan of Action documents,
Implementation Plans, and Safety Basis Flowdown/Implementation
Matrices. Dynamic Solutions key personnel possess
a minimum education of a bachelor of science in
engineering and are proficient in Microsoft Word,
Projects, Excel, PowerPoint, and AutoCAD. In addition,
Dynamic Solutions has developed custom software
applications that enable quick turn around of
process animations for use in training and project
orientation.
Our technical background, understanding of the
DOE Orders, proficiency in computer usage, and
familiarity of subcontractor flowdown requirements
can quickly expedient project deliverables to
meet operational startup of activities. The principle
owner, Julie Wallen, is a qualified Team Leader
for ORR/RA. Her Qualification Summary is presented
below:
Summary of Technical Qualifications:
- Bachelor of Science Degree in Mechanical Engineering
- Eight years experience of operational readiness
evaluations for the start-up and restart of
nuclear facilities/activities at the Oak Ridge
Reservation.
- Five years experience in conceptual design,
systems requirements, and technical reviews
of detail designs of construction projects (piping
and instrumentation diagrams, and construction
drawings & specifications).
- Experienced with the development of procedural
documentation, project planning documents, mechanical
integrity programs, and preventive maintenance
programs.
Summary of Assessment/ORR/RA/Inspection Qualifications:
- Eight years experience participating/assisting
contractor ORR/RAs
- Attended 2-day DOE Readiness Preparation Workshops,
May 2003 & May 2004
- Support to six ORRs in the DOE Oak Ridge Facility
1. K-25/K-25 High Risk Process Gas Equipment
Removal - ORR
2. Transuranic/Alpha Low-Level Waste Treatment
Project Waste Processing Facility ORR
3. MSRE Fuel Salt Deposition ORR
4. Loading Spent Nuclear Fuel in Shipping Cask
ORR
5. Molten Salt Reactor Experiment (MSRE) Uranium
Material Disposition ORR
6. Transported Waste Receiving Facility
ORR
- Prepared 26 Plan of Action documents for ORR/RAs
and numerous Implementation Plans for ORR/RAs
and Safety Basis Implementation Validation Review
(IVR) processes
- Assisted line management with 27 ORR/RAs
processes
- Contractor Independent Team Leader or Participant
for (3) ORRs and (4) RAs
As part of this service, Dynamic Solutions
provides the following specific support services:
Readiness Preparation Support
Clearly define the scope of the activity and review,
determine the review type, prepare the startup
notification report, prepare the plan of action
with stated criterion and review areas justifiably
excluded from review, and prepare comment resolutions.
Develop and maintain Readiness Preparation Plan
& Schedule by integration of project planning
for readiness compliant with DOE O 425.1C (providing
resource-loaded schedules of project activities
linked with prerequisites and criterion of readiness).
Determine critical path actions; develop project
documents; provide process animation utilizing
DSLLCs proprietary software and other presentation
material; compile acceptable readiness evidence;
and mentor/coach in the readiness process. Document
line managements self-assessment, coordinate
meetings, and prepare corrective action plans
to pre- and post-start findings.
ORR/RA Coordination Support
Prepare implementation plan with criterion acceptance
documentation forms. Assist with the assessment
process, identify team members responsibilities,
provide writing guidance, assist with team members
qualification forms, prepare biographical summaries,
prepare meeting notes, coordinate the needs of
the team to conduct the assessment, assist the
team members with assessment focus, and prepare
final report.
Technical Support
Prepare facility layout and/or process flow drawings
defining the physical scope of the assessment
and components within the scope of the review.
Prepare presentation material. Prepare project
startup work plan, safety basis flowdown requirements
and implementation, training plans and material,
systems descriptions for configuration control,
project plans and procedures. Provide review comments
to project material and documents.
As part of these services, Dynamic Solutions
prepares the following likely deliverable items:
- Readiness Preparation Plan & Schedule
- Facility-specific SMP document comment reviews
- Activity-specific planning documents (Staffing
Plan, Training Plan, Startup Plan)
- Drawings / Presentation Material (PowerPoint;
animation; poster-boards)
- Startup Notification Report (SNR)
- Plan of Action (POA)
- Compilation of an Evidence File with Index
as determine to adequately meet readiness objective
and criteria
- Management Self Assessment Report
- Project Open Items List
- Implementation Plan (IP)
- Criteria and Review Approach Documents (CRADs)
- Meeting Notes
- Final Report
- Corrective Action Plan
The following is a list of successfully completed
ORR/RA projects presented in their chronological
order of completion:
- K-25/K-25 High Risk Process Gas Equipment
Removal - ORR
- Transuranic Waste Retrieval Project - RA
- Transuranic/Alpha Low-Level Waste Treatment
Project Waste Processing Facility ORR
- Molten Salt Reactor Experiment (MSRE) Uranium
Material Disposition ORR
- MSRE Fuel Salt Deposition ORR
- Loading Spent Nuclear Fuel in Shipping Cask
RA with DOE in series
- MSRE NaF Traps Depressurization Internal
RA
- T1, T2, HFIR Tank Remediation RA with
DOE in series
- Environmental Management Waste Management
Facility RA with DOE in series
- GuniteTM and Associated Tanks Stabilization
- Internal Field Review with Evaluation Review
Board (ERB)
- Hydrofracture Wells Plugging & Abandonment
- Internal Independent RA with ERB and DOE presentation
- Surface Impoundments Operable Units Remediation
- Internal Independent RA with ERB and DOE presentation
- MSRE Uranium Deposit Removal ORR
- Tank W-1A Removal Action, IT Corporation -
Internal Independent RA with ERB and DOE presentation
- Small Inactive Tanks Remediation, The Providence
Group - Internal Independent RA with ERB and
DOE presentation
- Tank TH-4/Russian Pulsating Mixing Pump -
RA with DOE in series
- W-Tank Mixer Restart and Transfer Project
at ORNL - RA with DOE in series
- Melton Valley Storage Tanks Wastewater Triad
Project - Internal Field Evaluations (IFEs):
Cesium Removal System IFE; Out-of-Tank Evaporator
IFE; Solid/Liquid Separation IFE
- Building 7856, Melton Valley Storage Tanks-
Capacity Increase - RA with the DOE in series
- Building 7572, Waste Storage Facility - RA
- Building 7966, Monitoring and Control Station
Readiness Self-Assessment (RSA)
- Building 2531, C-Tanks Transfer, Sludge Removal
by AEA Technologys Fluidic Pulse Jet Mixing
System - Readiness Determination with ERB and
DOE presentation
- Building 2537, Bethel Valley Evaporator Storage
Tanks Sludge Mixing Demonstration and Transfer
Project - RSA
- Building 3092, Central Off-Gas Scrubber -
RSA
- Building 7574, CH TRU Waste Storage Facility
- RA
- Building 2649, Transported Waste Receiving
Facility - ORR
- LR56M, Liquid-low Level Waste Transfer Truck
- RSA
|